The structural roof has completed and the roof covering is in progress.
The brickwall and plastering works have to be speed up as the award of the Interior Design works is going to be awarded soon. This hall is going to be a remarkable hall for the school.
Beside the Multi Purpose Hall, there will be a Auditorium Hall (Lecture Theatre) with a minimum capacity of 280 seats. This hall is now in the construction of reinforced concrete stage and anticipated to complete the RC work by the 10th of this Month.